Free PMP Exam Study

  • Home
  • PMP Certification Guide
  • PMP Practice Exam
  • PMP Sample Questions
Home » PMP Practice Exam » 177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 1

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 1

02/26/2015 Brenda Wilson 0 Comment

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 1

If you are worrying about your PMP exam and you want to pass the exam at this time, however, it is not easy to get the PMP certification because there are a lot of area which will be included in the examination namely initiating the project, planning the project, executing the project, monitoring and controlling the project and closing the project. Get further pmp information here. Thus, some people have failed at the first time, second one, even the third time, it is normal. To ensure that you have enough knowledge to pass your exam that you should have a good preparation before taking the exam. Here’s 177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 1 in which you can practice easily and remember deeply information included in your real exam. Let’s enjoy to discover project cost management on the domain II. Don’t forget to be continuous at part 2. Good luck!

You might be also interested in PMP exam practice on domain II:
Efficiently 217 Free Online PMP Exam Practice Questions On Planning The Project – Part 1
Efficiently 217 Free Online PMP Exam Practice Questions On Planning The Project – Part 2
119 Free Online PMP Practice Exam Questions On Planning The Project
Practice Immediately 14 PMP Exam Prep Online On the Domain II
Take 24% of Planning The Project With 12 Free PMP Practice Exams

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project - Page 1

• Planned value• Earned value• Actual cost
Earned value management (EVM) rules of performance measurement are set. For example, the cost management plan could:• Define the WBS and points at which measurement of control accounts will be performed,• Establish the earned value measurement techniques (e.g., weighted milestones, fixed formula, percent complete, etc.) to be employed, and• Specify the earned value management computation equations for determining the project estimate at completion (EAC) forecasts and other tracking methodologies
• Health• Safety• Security• Performance• Environmental• Insurance• Intellectual Property Rights• Licenses• Permits
Planned Value
• Schedule Performance Index• Cost Performance Index
Includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget
Is a measure of progress achieved compared to progress planned on a project. It is sometimes used in conjunction with the cost performance index (CPI) to forecast the final project completion estimates. The SPI is equal to the ratio of the EV to the PV
1. Scope Baseline2. Project Schedule3. Human Resource Plan4. Risk Register5. Enterprise Environmental Factors6. Organizational Process Assets
The calculated CV, SV, CPI, and SPI values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders
This and related detailed statements of work provide an identification of the deliverables and a description of the work in each WBS component required to produce each deliverable
Earned Value Management
Is the value of work performed expressed in terms of theapproved budget assigned to that work for an activity or work breakdown structure component. It is the authorized work that has been completed, plus the authorized budget for such completed work
Since SPI is less than 1, this means that project is behind schedule; hence it is recommended to crash the project to bring it on schedule. Please note that crashing may increase costs. Since your project has CPI greater than 1, cost will not be a concern
Is a measure of the value of work completed compared to the actual cost or progress made on the project. It is considered the most critical EVM metric and measures the cost efficiency for the work completed. The CPI is equal to the ratio of the EV to the AC
• Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. • The cost baseline will include projected expenditures plus anticipated liabilities. • Funding often occurs in incremental amounts that are not continuous, which appear as steps• The total funds required are those included in the cost baseline, plus management reserves, if any
means that benefits (i.e. expected revenue) is less than the cost. Hence it is not beneficial to do the project
The type and quantity of resources and the amount of time which those resources are applied to complete the work of the project are major factors in determining the project cost. Schedule activity resources and their respective durations are used as key inputs to this process
means that benefits (i.e. expected revenue) is greater than the cost. Hence it is beneficial to do the project
• Analogous cost estimating uses the values of parameters, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity, from a previous, similar project as the basis for estimating the same parameter or measure for a current project. • When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project. • It is a gross value estimating approach, sometimes adjusted for known differenc
Planning Process Group
• In this forecast, the ETC work will be performed at an efficiency rate that considers both the cost and schedule performance indices. • It assumes both a negative cost performance to date, and a requirement to meet a firm schedule commitment by the project. • This method is most useful when the project schedule is a factor impacting the ETC effort. • Variations of this method weigh the CPI and SPI at different values (e.g., 80/20, 50/50, or some other ratio) according to the project manager's judgment.
Indicates that more work was completed than was planned
EAC = BAC / cumulative CPI
The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline
Number of years required for an organization to recapture an initial investment. Discount period is not taken into account in calculations for payback period
• This EAC method accepts the actual project performance to date (whether favorable or unfavorable) as represented by the actual costs, and predicts that all future ETC work will be accomplished at the budgeted rate. • When actual performance is unfavorable, the assumption that future performance will improve should be accepted only when supported by project risk analysis.
• method builds upon the actual costs and experience incurred for the work completed, and requires a new estimate to complete the remaining project work. • This method may be problematic in that it interferes with the conduct of project work. • The personnel who are performing the project work have to stop working to provide a detailed bottom-up ETC of the remaining work. • Typically there is no separate budget to perform the ETC, so additional costs are incurred for the project to conduct the ETC• The proj
The work breakdown structure (WBS) provides the framework for the cost management plan, allowing for consistency with the estimates, budgets, and control of costs. The WBS component used for the project cost accounting is called the control account (CA). Each control account is assigned a unique code or account number(s) that links directly to the performing organization's accounting system.
decreased duration and increased costs. This is reflected with CPI is less than 1 and SPI is greater than 1
Descriptions of each of the three cost management processes are documented
(BAC - EV) / (BAC - AC)
• Level of accuracy• Units of measure• Organizational procedures links• Control thresholds• Rules of performance management• Reporting formats• Process descriptions
Project staffing attributes, personnel rates, and related rewards/recognition are necessary components for developing the project cost estimates
the performance measurement baseline (PMB)
• Any historical relationships that result in parametric estimates or analogous estimates involve the use of project characteristics (parameters) to develop mathematical models to predict total project costs. • Such models can be simple (e.g., residential home construction is based on a certain cost per square foot of space) or complex (e.g., one model of software development costing uses multiple separate adjustment factors, each of which has numerous points within it)
The process of developing an approximation of the monetary resources needed to complete project activities
Indicates less work was completed than was planned
• If the cumulative CPI falls below the baseline plan, all future work of the project will need to immediately be performed in the range of the TCPI (BAC) to stay within the authorized BAC. • Whether this level of performance is achievable is a judgment call based on a number of considerations, including risks, schedule, and technical performance. • Once management acknowledges that the BAC is no longer attainable, the project manager will prepare a new estimate at completion (EAC) for the work, and once ap
The formats and frequency for the various cost reports are defined
A commonly used method of performancemeasurement. It integrates project scope, cost, and schedule measures to help the project managementteam assess and measure project performance and progress. It is a project management techniquethat requires the formation of an integrated baseline against which performance can be measured forthe duration of the project
Indicates a cost overrun for work completed
The causes of positive and negative variances and is part of the Perform Integrated Change Control process

Related Posts

  • 20 Free PMP Exam Prep Questions on Planning the Project Online20 Free PMP Exam Prep Questions on Planning the Project Online
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 356 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3

Share:

  • Facebook
  • Twitter
  • LinkedIn
  • Tumblr
  • Pinterest
  • Email
  • More
  • Print
  • Reddit
  • Pocket

Related

Category: PMP Practice Exam/ PMP Sample Questions Tags: free pmp practice exams/ free PMP practice exams by performance domain/ pmp certification practice exams/ pmp exam prep questions/ pmp mock exam/ pmp practice exam/ pmp practice exam questions/ pmp practice exams/ pmp practice test

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

PMP Practical Exam Prep

  • PMP Mock Exam – Initiating The Project
  • PMP Practice – Project Quality Management
  • PMP Test Questions – Project Resource Management
  • PMP Samples Questions – Human Resource Management
  • PMP Practice Exam – Project Time Management
  • PMP Tests – Project Communication Management
  • PMP Question Exams – Project Stakeholder Management
  • PMP Question bank – ITTO Project Scope Management
  • PMP Exam Questions – Project Risk Management
  • PMBOK 5th Edition PMP Practice Questions
  • PMP Samples Test – Planning The Project
  • PMP Practice Test – Project Integration Management
  • PMP Exam Samples – Project Management Framework

Recent Posts

  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3
  • 26 Necessary Free PMP Practice Exams Quiz Questions
  • 58 Free Project Time Management Questions for Information Technology Project Management 6th Edition by Schwalbe

Copyright © 2023 · Pmp Exams Prep · Privacy Policy · About · Contact

Copyright © 2023 · Paradise v3.2.0 on Genesis Framework · WordPress · Log in