Free PMP Exam Study

  • Home
  • PMP Certification Guide
  • PMP Practice Exam
  • PMP Sample Questions
Home » PMP Practice Exam » 177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 2

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 2

02/26/2015 Brenda Wilson 0 Comment

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 2

Hi again, welcome to you move on the part 2 to practice with 177 Helpful Free Online PMP Exam Practice Questions On Planning The Project – Part 2. As you know already, it is not easy to get the PMP certification because there are a lot of area which will be included in the examination namely initiating the project, planning the project, executing the project, monitoring and controlling the project and closing the project. Get further pmp information here.  Thus, some people have failed at the first time, second one, even the third time, it is normal. To ensure that you have enough knowledge to pass your exam that you should have a good preparation before taking the exam. Practice free online PMP prep exam question that is the best way to help yourself pass the exam. Let’s continuous starting at part 2 and you should note your result to know what you need to pratice more. Good time!

You might be also interested in:
All You Should Know To Create A Powerful PMP Exam Brain Dump
Save Time And Earn Chances Of Acing PMP Exam with Top-Rated PMP Study Materials
Killer Tricks And Tips To Accelerate Your PMP Exam Marathon
Mad About PMP Distracting Exam Questions
What Is True Amid Myths About PMP Exam Passing Score?
Save Time And Earn Chances Of Acing PMP Exam with Top-Rated PMP Study Materials

177 Helpful Free Online PMP Exam Practice Questions On Planning The Project - Page 1

• Cost performance measurements (CV, CPI) are used to assess the magnitude of variation to the original cost baseline. • Important aspects of project cost control include determining the cause and degree of variance relative to the cost performance baseline and deciding whether corrective or preventive action is required. •The percentage range of acceptable variances will tend to decrease as more work is accomplished. • The larger percentage variances allowed at the start of the project can decrease as the
• The risk register
• Is a method of estimating a component of work• The cost of individual work packages or activities is estimated with the greatest level of specified detail. • The detailed cost is then summarized or "rolled up" to higher levels for subsequent reporting and tracking purposes. • The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package
• Cost estimates are influenced by numerous variables such as labor rates, material costs, inflation, risk factors, and other variables. • Provides valuable insight about the environment and information from prior similar projects. • Can also be used to determine whether to combine methods of estimating and how to reconcile differences between them
a project selection criteria
unit cost rates in calculations, but doesn't determine those rates
Budget reserve analysis can establish both the contingency reserves and the management reserves for the project
• The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. • A variance between the funding limits and the planned expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. • This can be accomplished by placing imposed date constraints for work into the project schedule
Reflect the cost and schedule performance of any project for comparison against all other projects or within a portfolio of projects. The variances and indices are useful for determining project status and providing a basis for estimating project cost and schedule outcome
1. Expert Judgement2. Analogous Estimating3. Parametric Estimating4. Bottom-up Estimating5. Three-Point Estimates6. Reserve Analysis7. Cost of Quality (COQ)8. Project Management Estimating Software9. Vendor Bid Analysis
• The project manager may be required to obtain approval before obligating or spending management reserve. • Are not a part of the project cost baseline, but may be included in the total budget for the project. • They are not included as a part of the earned value measurement calculations
Is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC
Compare cost performance over time, schedule activities or work packages overrunning and under running the budget, and estimated funds needed to complete work in progress
A prediction that is based on the information known at a given point in time. It includes the identification and consideration of costing alternatives to initiate and complete the project
Is a measure of schedule performance on a project.It is equal to the earned value (EV) minus the planned value (PV)
• Variance analysis• Trend analysis• Earned value performance
Cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS (such as control accounts) and ultimately for the entire project
• Should be reviewed to consider risk mitigation costs• Risks, which can be either threats or opportunities, typically have an impact on both activity and overall project costs. • As a general rule, when the project experiences a negative risk event, the near-term cost of the project will usually increase, and there will sometimes be a delay in the project schedule
• Use a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. • This technique can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. • Can be applied to a total project or to segments of a project, in conjunction with other estimating methods.
The total of Planned Value
The project management plan contains the following information that is used to control cost:• Cost Performance Baseline• Cost Management Plan
Zero, because all planned values will have been earned
The cost management plan describes how the project costs will be managed and controlled
• Causes of variances,• Corrective action chosen and the reasons, and• Other types of lessons learned from project cost control
a manual, bottom-up summation by the project manager and project team
Those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure
Planning Process Group
Estimate Activity Resources involves determining the availability and quantities required of staff and material needed to perform schedule activities. It is closely coordinated with cost estimating
Resource cost rate information is often available from commercial databases that track skills and human resource costs, and provide standard costs for material and equipment. Published seller price lists are another source of information.
• Analysis of project performance can result in a change request to the cost performance baseline or other components of the project management plan. • Change requests can include preventive or corrective actions and are processed for review and disposition through the Perform Integrated Change Control process
Cost Performance Index
1. Project Management Plan2. Project Funding Requirements3. Work Performance Information4. Organizational Process Assets
• Make versus buy• Buy versus lease• Sharing of resources
Variance thresholds for monitoring cost performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the baseline plan
EAC = AC + BAC - EV
• Cost estimates• Basis of estimates
• Project management cost estimating software applications, computerized spreadsheets, simulation, and statistical tools are becoming more widely accepted to assist with cost estimating. • Such tools can simplify the use of some cost estimating techniques and thereby facilitate rapid consideration of cost estimate alternatives
Applicable contract information and costs relating to products, services, or results that have been purchased are included when determining the budget
Budgets reserved for unplanned changes to project scope and cost
• The EV being measured must be related to the PV baseline (PMB)• The EV measured cannot be greater than the authorized PV budget for a component• The term EV is often used to describe the percentage completion of a project• A progress measurement criteria should be established for each WBS component to measure work in progress• Project managers monitor EV, both incrementally to determine current status and cumulatively to determine the long-term performance trends
Used to monitor the three EVM dimensions (PV, EV, and AC), to display graphical trends, and to forecast a range of possible final project results
• Historical information used to develop the model is accurate,• Parameters used in the model are readily quantifi able, and• Models are scalable, such that they work for a large project, a small project, and phases of a project
Resource calendars provide information on which resources are assigned to the project and when they are assigned. This information can be used to indicate resource costs over the duration of the project
whereby a task is considered to be either 0 percent complete or 100 percent complete, but nothing in between
• Are generally expressed in units of some currency (i.e., dollars, euro, yen, etc.), although in some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating the effects of currency fluctuations• Sources of input information are derived from the outputs of project processes in other Knowledge Areas• Estimated for all resources that will be charged to the project. This includes, but is not limited to, labor, materials, equipment, services, and f
• This method assumes what the project has experienced to date can be expected to continue in the future. • The ETC work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date.
• Influencing the factors that create changes to the authorized cost baseline,• Ensuring that all change requests are acted on in a timely manner,• Managing the actual changes when and as they occur,• Ensuring that cost expenditures do not exceed the authorized funding, by period and in total for the project,• Monitoring cost performance to isolate and understand variances from the approved cost baseline,• Monitoring work performance against funds expended• Preventing unapproved changes from being included
• include the cost of operations, which is beyond the scope of the project• Includes direct and indirect costs• Includes periodic or continuing cost of operations and maintenance• life cycle costs are not the responsibility of the project manager
critical path methodology (CPM) scheduling and risk management
Earned value management compares the baseline plan to actual schedule and cost performance
• Schedule variance• Cost variance

Related Posts

  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 356 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3
  • 26 Necessary Free PMP Practice Exams Quiz Questions26 Necessary Free PMP Practice Exams Quiz Questions

Share:

  • Facebook
  • Twitter
  • LinkedIn
  • Tumblr
  • Pinterest
  • Email
  • More
  • Print
  • Reddit
  • Pocket

Related

Category: PMP Practice Exam/ PMP Sample Questions Tags: free pmp practice exams/ pmp certification practice exams/ pmp exam prep questions/ pmp mock exam/ pmp practice exam/ pmp practice exam questions/ pmp practice exams/ pmp practice test

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

PMP Practical Exam Prep

  • PMP Mock Exam – Initiating The Project
  • PMP Practice – Project Quality Management
  • PMP Test Questions – Project Resource Management
  • PMP Samples Questions – Human Resource Management
  • PMP Practice Exam – Project Time Management
  • PMP Tests – Project Communication Management
  • PMP Question Exams – Project Stakeholder Management
  • PMP Question bank – ITTO Project Scope Management
  • PMP Exam Questions – Project Risk Management
  • PMBOK 5th Edition PMP Practice Questions
  • PMP Samples Test – Planning The Project
  • PMP Practice Test – Project Integration Management
  • PMP Exam Samples – Project Management Framework

Recent Posts

  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3
  • 26 Necessary Free PMP Practice Exams Quiz Questions
  • 58 Free Project Time Management Questions for Information Technology Project Management 6th Edition by Schwalbe

Copyright © 2023 · Pmp Exams Prep · Privacy Policy · About · Contact

Copyright © 2023 · Paradise v3.2.0 on Genesis Framework · WordPress · Log in