42 Necessary PMP Sample Test Questions On Project Initiation

02/26/2015 Marie Hall 0 Comment

42 Necessary PMP Sample Test Questions On Project Initiation

42 necessary PMP sample test questions on project initiation help you juggle the misleading forest of PMP exam questions through hit-to-the-point coverage of performance domain 1. It’s cliche to say but actual questions for PMP has been, for long, tricky; that’s why lots of PMP aspirants have considered this test a real challenge. Still, once you attempt to crush qualified  PMP practice tests designed in ways geared towards your critical thinking enhancement, the battle against this exam won’t be that tedious. Below questions are friendly formatted intended for your most comforting practice experience and development of critical thinking. There come out prompt answers and your score after you hit handy ‘submit’ button. As such, you can figure your weaker knowledge and learn important lessons along the way. Let work hard on it and other practices, and the great efforts will bring out the best for you, accordingly.

Other cups of tea for you:
Must-Read Tricks for Selecting Best Answer to Tricky PMP Exam Question
Save Time And Earn Chances Of Acing PMP Exam with Top-Rated PMP Study Materials
All You Should Know To Create A Powerful PMP Exam Brain Dump

42 Necessary PMP Sample Test Questions On Project Initiation

_____ for project constraints are established during the ____ stage.
1) no HOME when project is complete2) may be duplication of job functions3) less efficient use of resources.
1) two bosses2) need more well-defined policies and procedures
In the real world there are great differences across organizations in project management methods. ____ to ____
those ultimately affected, either positively or negatively.
Change management processes (approvals and revision procedures)
Project structure and ____ is defined in the planning stage.
During the project initiation phase, and before the project is approved, we need to ask: "Is the proposed project ___ with the organization?"
A ____ is made at department or organization levels. (Initiation)
What are the 5 components of the project lifecycle???
A project ____ makes the case. (Initiation)
tool to analyze possible "impacts."
A ___ is made for why the project is needed. (Initiation)
project life cycles ___
What stage does this take place: communication plants are developed, documentation, change management process (approvals and revision), monitor and control.
Project structure and governance defined; project team is formed --> what stage does this take place in?
1) easier management of specialists2) career path for PM is specialized3) goals are more focused
_____ is critical for project success. When problems arise you want them to come to your rescue. (initiation)
In the real world, linear (waterfall) models of the project lifecycle ignore the iterative, cyclical nature of project management practice. Other PM models reflect this.
monitor and control; project managers are "control freaks" PMS need feedback mechanisms to anticipate problems
What stage does this take place:product or service is delivered, product or service testing, training procedures are implemented.
PMS must be good at overcoming resistance through good __ ___
entire firm is organized by projects.
Outcome of planning is the ___ _____.
A PM must be a ___ ___ between the strategic and operational. ( this is where they fall in terms of level of authority within the organization )
1) efficient project organization2) project manager has optimal control3) communication is easier and more effective
projects represent ___ within an organization
summary of lessons learned, experiences gained, ideas for future projects for the purpose of the organizational learning.
1) people tend to focus more on department concerns than organizational concerns2) career path is more in department business than project management3) the project manager has little or not authority
most common type of organization, department silos, functional manager has primary authority.
Triple constraints are clearly defined in what stage of the lifecycle?
project stakeholders are identified in what stage? These are the people who can positively or negatively affect the outcome of the project.
1) cooperative relationship between project team and functional area2) improved control for PM over functional organization
the proposed project needs to be aligned with what three things in an organization???
people instinctively ___ change
communication plans are developed
attempts to maximize the strengths of functional and projectized organization, two "bosses" PM and functional manager, strong matrix: PM has, and weak matrix: functional manager has power.
Documentation: stakeholders and resources (contracts, requisitions, authorizations, etc)
What stage does this take place:Formal administrative closure, project team and team members evaluations, lessons learned are developed and archived, project audit.
are the intermediaries in the aid delivery process.
documentation of customer acceptance, vendor contracts are terminated, resources are decommissioned or reassigned.
The body of data, information, and knowledge relevant to an individual organization's existence that has two major repositories: the organization's archives and individual's memories. (lessons learned)

Related Posts

  • 20 Free Project Initiation Questions from  CompTIA Project+ Study Guide Authorized Courseware: Exam PK0-003 by Heldman20 Free Project Initiation Questions from CompTIA Project+ Study Guide Authorized Courseware: Exam PK0-003 by Heldman
  • 65 Free Online PMP Practice Exam On Initiating Project65 Free Online PMP Practice Exam On Initiating Project
  • 10 Free Online PMP Exam Questions On Project Initiation10 Free Online PMP Exam Questions On Project Initiation
  • 45 Free Online PMP Sample Questions On Initiating Project45 Free Online PMP Sample Questions On Initiating Project

Share:

  • Facebook
  • Twitter
  • LinkedIn
  • Tumblr
  • Pinterest
  • Email
  • More
  • Print
  • Reddit
  • Pocket

Related

Category: PMP Practice Exam/ PMP Sample Questions Tags: free PMP practice exams by performance domain/ initiating a project/ pmp exam sample questions/ pmp question bank/ pmp sample question/ sample pmp questions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

PMP Practical Exam Prep

  • PMP Mock Exam – Initiating The Project
  • PMP Practice – Project Quality Management
  • PMP Test Questions – Project Resource Management
  • PMP Samples Questions – Human Resource Management
  • PMP Practice Exam – Project Time Management
  • PMP Tests – Project Communication Management
  • PMP Question Exams – Project Stakeholder Management
  • PMP Question bank – ITTO Project Scope Management
  • PMP Exam Questions – Project Risk Management
  • PMBOK 5th Edition PMP Practice Questions
  • PMP Samples Test – Planning The Project
  • PMP Practice Test – Project Integration Management
  • PMP Exam Samples – Project Management Framework

Recent Posts

  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3
  • 26 Necessary Free PMP Practice Exams Quiz Questions
  • 58 Free Project Time Management Questions for Information Technology Project Management 6th Edition by Schwalbe

Copyright © 2023 · Pmp Exams Prep · Privacy Policy · About · Contact

Copyright © 2023 · Paradise v3.2.0 on Genesis Framework · WordPress · Log in