100 PMBOK 5th Edition PMP Practice Questions Free Online

04/13/2015 Marie Hall 0 Comment

100 PMBOK 5th Edition PMP Practice Questions Free Online

100 PMBOK 5th edition PMP practice questions free online covers knowledge around the updated version of PMBOK Guide. What makes this PMP practice questions test free highly trusted is its information presentation in an engaging and simple way. Indeed, the friendly layout allows your easy access to the questions, making your practice experience least tedious. You just need click on your best response to each question. There are two pages, each of which has an equal number of quizlets. Just hit the submit button at the bottom of page 2 to have your results automatically checked and graded. If you score at least 85%, you have a real seize on PMBOK 5th edition. If you reach lower than 85% of points, then you still need some more investment in it. Overall, you should use it to cement knowledge gaps and learning and be far much closer to the actual PMP exam. (This question bank is provided by izenbridge.com. Lots of thanks.)

You may need those good sample questions:
10 Free PMP Sample Questions and Answers Based on PMBOK 5th Edition by PM Prepcast
200 Free PMP Mock Exams Based on 5th PMBOK Edition

100 PMBOK 5th Edition PMP Practice Questions Free Online - Page 1

Which of the following BEST describes what a project charter may be used for, when project is in Execution phase?
You are planning to buy a house and went to a builder to get some idea of how much a house that fits in your requirement will cost you. Builder provides you estimation for the construction of a residential home based on cost a certain amount per square foot of living area. This is an example of what type of estimating?
‘Sam’ the project manager is working towards clearly describes the level of involvement expected from everyone involved in the project. The main purpose is to prevent rework, conflicts and coordination issues. Which of the following BEST describes the Sam’s efforts?
You are happy project manager of a project and in planning phase, everything is going great. On one fine day, you get the information from higher management that your customer has decided to terminate the project as the need for the product does not exist anymore. As a project manager, what step would you take FIRST?
As a project manager, you know that stakeholders can impact project success. To manage stakeholder expectations is an important priority. Out of the following which statement on project stakeholders is NOT correct?
In projects, expert judgment will often be used throughout the project integration processes. Which of the following does not provide expert judgment?
You have completed your project and performing project closure activities. What should you do LAST in this process?
When as project manager you have given choice to select project you can undertake out of three projects available, Out of following factors which you will NOT consider while taking decision
Out of all stakeholders, a stakeholder is voicing Negative opinions about part of project scope to other stakeholders. As a result now there is strong opposition to some deliverables even though everyone had agreed to the scope when it was defined. Which of the following is the BEST choice for the project manager?
All of the following statements are true EXCEPT for which one?
You are just promoted as the Project Manager and trying to learn all about project management. The project which is assigned to you is in planning process and you are trying to be sure to follow the entire set of core planning processes as they should be. You have started developing WBS, and realize activity definition is next. You are slightly confused about the difference between the two. How would the difference between two can be described?
You are working on a new project as the Project manager for mobile applications which is started with the objective to provide new easy to use features to the users. You and your team are working on the analysis that what features will be incorporated into the software. You are consulting with a SME group as well who can evaluate the features of the project going forward. The SME group along with quality team has the authority to suggest changes for the software for making it more useable. As a project manager which document will be impacted most in this scenario?
Your company manufactures small electric switches. It is introducing new product line of designer switches in various colors. These new products will be offered indefinitely starting with the spring catalog release. Which of the following is TRUE?
. ‘Sam’ the project manager is holding a team meeting and stakeholders to discuss and learn that what has hindered and what has helped the project and project team’s performance. All the following statements are true regarding this situation except for which one? Choose the least correct answer
You have been assigned to a project in which the objectives are to record customer messages to an automated system in case of customer queue is very long and then if customer wants to continue, connect customer to call agent when his/her turn comes. You are in charge of media communication for this project. VP marketing will share responsibility with you for this project. Which organizational structure do you work in?
As a project manager, you are performing administrative closure of the project. At the end of the process, you will have formal acceptance, project archives and ____
During which process the project manager review prior phase documentation and customer acceptance documentation from the Verify Scope process?
Sam is looking for 2 Java Programmers for his project which he is managing as project manager. He had worked with Raymond who is an expert Java programmer in project which is completed year back now. He has met with Joe who is just out of school and Sam liked his attitude and would like to take him in his team even if he is lesser effective what he is looking for. Where can Sam, the project manager, find the information for the availability of Raymond and Joe so that he can put both on the project and get the work started?
What is the BEST technique to determine project objectives?
Sam is the project manager and plans to involve his team for risk identification session. During the session Sam and his team have identified 130 risks. Sam realizes that 130 is quite big number and to evaluate each of these risks can cost enormous amount of his time as well as team’s time. And the effort may not be worth enough as not all of these risks are relevant and important. What Sam should do next?
While planning for your project as the project manager, you realized that your project has 4 critical paths. Which of the following BEST describes how it is going to affects your project?
Out of all the following listed contract types, which has got the highest risk for the seller?
Joe has been assigned as the project manager of a project which is in execution phase as the project manager who used to manage it left the company. And in the first meeting introduction with the customer his complaints Joe about the poor visibility of the project as the last manager was keeping customer informed. In this scenario what Joe should do first thing to resolve the issue?
You are the project manager of project which is at the closure stage. For administrative closure of the project what steps you will follow: Step 1 – Activities and actions required to transfer project’s products, services or result to the next phase or to production or operations. Step 2 – Actions and activities required to update risk plan and scope management plan. Step 3 – Actions required collecting project or phase records, audit results and lessons learned. Step 4 – Actions and activities required to satisfy completion or exit criteria for the phase or project
As a project manager, you receive an initial document of a project which states narrative description of product or service and results which required to be delivered by the project from the sponsor of the project. This document has the other references containing information that what are the needs of project depending on market demand or any government regulation and the scope characteristics of the product. What is the formal name of the document that you as Project manager have received?
For a multi-phased project, when does the Close Project or Phase process needs to be done and what all need to be done?
You and your team are involved in cost estimation of your project which is in planning phase and in the process of project cost management. Which of the following tools and techniques is NOT applicable for your project’s cost estimation.
Sam is the project manager and asked his team to come up with estimates of a new module need to be added in the current software. The team has come up with estimate of 25 weeks and informs you that it can be shortened by 2 weeks if everything goes good. But because of some dependencies on third party, project can be delayed by five weeks. How these numbers can help Sam to calculate three-point estimate for the project.
You are a project manager of an information technology project in an investment bank. While developing the project charter, you realize that there are several regulatory requirements which are not addressed in the business case. And failure to meet these regulatory requirements can lead to legal actions against the company. The implementation of these requirements will increase the project’s scope and budget, which may result in cancellation of the project. What should you do?
Which of the following is NOT required as input for Close project / phase process
You have started with a new project as the project manager which has 10 stakeholders and 15 team members. Moving forward two stakeholders and three team members are also added. How many more communication channels will this add to the project?
You are attending training on project management and the trainer had just started defining WBS. You are also a relatively new project manager and trying to learn about WBS. In the training break, you and other team members started discussing about what they have understood about WBS. Sam says that ‘WBS contains work packages that are described in a linear, unstructured list’. Joe says ‘Each item in the WBS represents a feature in the product scope’ and As per Lena ‘The WBS represents all of the work that must be done on the project’. Julie says that ‘WBS is created by the product sponsor and stakeholders’. Who defines WBS in most correct form?
You are considering hiring service of some vendors regarding a utility development in your project. You have started with Plan procurement process, as a seasoned project manager in your opinion which of the following statements is true regarding the procurement management plan?
Project charter is the initial document which is created by inputs such as SOW, business cases, organizational process assets and in contains information which includes?
Two project managers were debating on whole purpose of project charter. As per project manager ‘A’, project charter is required to authorize start of a project formally and this is the whole purpose of it. As per project manager ‘B’, project charter is required to authorize a project to start and provide authority to project manager to apply organization resources to the project which as per project manager A, project manager already have authority to use any organizational resource. Who is correct in their thinking here?
You are the project manager and working on a critical project that has strict deadline and no one can afford any schedule delay in completion. You are working on reducing the schedule duration of your project and decide to implement crashing for schedule reduction. Out of the following options can BEST describe your approach for implementing crashing?
You want one of your team lead to be trained for project management activities and have asked him to drive cost estimates for a new module of the project. He is an experienced and expert of the technology which needs to be used for this module. He is taking each activity, assigning its cost, and then aggregating it to a final cost estimate. Which type of costing estimation is he using?
While planning for a critical project delivery, you want to give yourself a few extra hours from budgeted time for a construction and testing phase to account for problems with unavailability of team resources for any reasons or delays in delivery. This scenario can be BEST described as ___
Which of the following is NOT input to the Identify Risk process?
Which Analytical techniques are BEST suitable to check the performance of project /phase at the time of close project/ phase?
Who issues the Project Charter ?
In an organization a restructuring shift from weak matrix to strong matrix organization, the power is shifted from the:
You are the project manager of a small project. Recently assigned to manage another project also . As both projects are ongoing, you need to divide your time among these two. The second project seems to be growing in size every day. With time passes, you feel more and more need of help. You have heard about a project manager in your organization who had managed project similar to second project. As project manager what should you do?
While working on Close procurement process, the project manager is responsible to complete each project procurement to complete Close project / phase. In this context, the final settlement of all outstanding issues, claims and disputes (if any) by negotiations is done through:
You are assigned to a new project that has been attempted, but unsuccessful several times in last few years. The reason for unsuccessful attempts was ‘Politics’ (differing views and directions by key stakeholders). This is an example of:
What is the typical thing that critical chain project management deals with?
Sam has given commitment to the client that project will be completed on day 30. The project has 10 activities and 15 resources are assigned to it. The critical path has duration 25 days and 12 activities. What is the project slack?
As a project manager, you have assigned communication distribution task to your team lead Ray as you are preparing him for the better roles now. You have told him to send project’s weekly status report to all stakeholders via email after reviewing the reports. What kind of communication delivery model you are suggesting to Ray for information distribution?
You are creating your authorized Cost Baseline of your project. What process are you in?
You are the project manager of the project which is in planning phase. You are done with scope, time, cost, human resource and quality planning and now working at risk response planning. In the process you realize that there is a very critical risk which may have a high cost impact on the project completion. So, you create a fallback plan, which of the following looks LEAST appropriate for fallback plan?
What are the inputs to the Develop Project Charter process?
You are a seasoned project manager and managing a project the project manager. In a conference call your client tells you about some federal changes that need you to meet an earlier deadline for the project as client cannot perform their business properly without the new product. After conference call you call for a team meeting and inform them about the early deadline. You tell your team that either crashing or fast-tracking the schedule can be done. You team members are not sure about these two ways and asks how these impact the project?
As the project manager you have been asked to calculate the internal rate of return (IRR) of a project? What do you calculate to find out IRR or what represents IRR?

Related Posts

  • 83 PMBOK 5th Edition PMP Practice Questions Free on Project Scope Management83 PMBOK 5th Edition PMP Practice Questions Free on Project Scope Management
  • 46 Best Free PMP Practice Exam for CAPM/PMP All in One Exam Guide Chapter 446 Best Free PMP Practice Exam for CAPM/PMP All in One Exam Guide Chapter 4
  • 19 Best Free PMP Practice Exam for CAPM/PMP All in One Exam Guide Chapter 119 Best Free PMP Practice Exam for CAPM/PMP All in One Exam Guide Chapter 1
  • 511 Free PMP Question Bank on PMP Definitions 5th Edition511 Free PMP Question Bank on PMP Definitions 5th Edition

Share:

  • Facebook
  • Twitter
  • LinkedIn
  • Tumblr
  • Pinterest
  • Email
  • More
  • Print
  • Reddit
  • Pocket

Related

Category: PMP Practice Exam/ PMP Sample Questions Tags: pmbok guide 5th edition/ pmp exam sample questions/ pmp practice questions/ pmp sample questions pmbok 5th edition/ sample pmp questions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

PMP Practical Exam Prep

  • PMP Mock Exam – Initiating The Project
  • PMP Practice – Project Quality Management
  • PMP Test Questions – Project Resource Management
  • PMP Samples Questions – Human Resource Management
  • PMP Practice Exam – Project Time Management
  • PMP Tests – Project Communication Management
  • PMP Question Exams – Project Stakeholder Management
  • PMP Question bank – ITTO Project Scope Management
  • PMP Exam Questions – Project Risk Management
  • PMBOK 5th Edition PMP Practice Questions
  • PMP Samples Test – Planning The Project
  • PMP Practice Test – Project Integration Management
  • PMP Exam Samples – Project Management Framework

Recent Posts

  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 2)
  • 401 Free PMP Practice Exams Quiz Questions and Answers (Part 1)
  • 56 Other Practice PMP Exam for CAPM/PMP All in One Exam Guide Chapter 3
  • 26 Necessary Free PMP Practice Exams Quiz Questions
  • 58 Free Project Time Management Questions for Information Technology Project Management 6th Edition by Schwalbe

Copyright © 2023 · Pmp Exams Prep · Privacy Policy · About · Contact

Copyright © 2023 · Paradise v3.2.0 on Genesis Framework · WordPress · Log in